Q1: Which of the following are the guidelines for the construction of a network diagram?

A Each activity is represented by one and only one arrow in the network.

B Dangling must be avoided in a network diagram.

C Dummy activity consumes no time or resource.

D all of the above

ANS:D - all of the above

Explanation: No answer description is available. 