Q1:

Which of the following statement is correct?

A When slack of an activity is zero, it falls only on critical path.

B CPM technique is useful to minimise the direct and indirect expenses.

C Critical path of a net work represents the minimum time required for completion of project.

D all of the above

ANS:D - all of the above

Explanation: No answer description is available.