- Industrial Engineering and Production Management - Section 1
- Industrial Engineering and Production Management - Section 2
- Industrial Engineering and Production Management - Section 3
- Industrial Engineering and Production Management - Section 4


Industrial Engineering and Production Management - Engineering
Q1: Which of the following statement is correct?A When slack of an activity is zero, it falls only on critical path.
B CPM technique is useful to minimise the direct and indirect expenses.
C Critical path of a net work represents the minimum time required for completion of project.
D all of the above
ANS:D - all of the above Explanation: No answer description is available. |


For help Students Orientation
Mcqs Questions
One stop destination for examination, preparation, recruitment, and more. Specially designed online test to solve all your preparation worries. Go wherever you want to and practice whenever you want, using the online test platform.