| Q1: Which of the following statement is correct?A When slack of an activity is zero, it falls only on critical path.
  B CPM technique is useful to minimise the direct and indirect expenses.
  C Critical path of a net work represents the minimum time required for completion of project.
  D all of the above
  ANS:D - all of the above Explanation: No answer description is available. | 
 
             
                            