Construction Management - Engineering
Q1: Which one of the following represents an activityA
excavation for foundation
B curing of concrete
C setting of question paper
D
preparation of breakfast
E
all the above.
ANS:E - all the above. Activity means a consume resources & And has a Definite beginning & end. |