Tunnelling - Engineering
Q1: Which one of the following statements is not correct for heading and benching method of tunnelling ?A
Drilling and mucking can be done simultaneously
B
Benching provides a plateform for working on heading
C
Removal of muck from the heading is very easy
D
None of these.
ANS:C - Removal of muck from the heading is very easy Option A is correct. |