Construction Management - Engineering

Q1:

While scheduling a project by C.P.M.

A a project is divided into various activities

B required time for each activity is established

C sequence of various activities is made according to their importance

D net work is drawn by connecting the activities and the events

E All the above.

ANS:E - All the above.

No answer description is available.