Q1: Work study is mainly aimed at

A determining the most efficient method of performing a job

B establishing the minimum time of completion of a job

C developing the standard method and standard time of a job

D economising the motions involved on the part of the worker while performing a job

ANS:A - determining the most efficient method of performing a job

Explanation: No answer description is available. 