The following pie-chart shows the sources of funds to be collected by the National Highways Authority of India (NHAI) for its Phase II projects. Study the pie-chart and answers the question that follow.

Sources of funds to be arranged by NHAI for Phase II projects (in crores Rs.)

Q1:

If the toll is to be collected through an outsourced agency by allowing a maximum 10% commission, how much amount should be permitted to be collected by the outsourced agency, so that the project is supported with Rs. 4910 crores?

A Rs. 6213 crores

B Rs. 5827 crores

C Rs. 5401 crores

D Rs. 5316 crores

ANS:C - Rs. 5401 crores

Amount permitted = (Funds required from Toll for projects of Phase II) +
   (10% of these funds)
  = Rs. 4910 crores + Rs. (10% of 4910) crores
  = Rs. (4910 + 491) crores
  = Rs. 5401 crores.